RDF-1200x570

Following installation works at the plant, the project has now received its Readiness to Receive RDF certificate from Fichtner Consulting Engineers, acting as the Project Manager. The certificate means RDF can be brought onto site to commence the hot commissioning works. The first fuel deliveries arrived at the plant on 14th August 2018