Fuel prepared by Refuge Derived Fuel (RDF) delivered to the plant has been fed into the gasifier for combustion. The video footage below was taken through […]
Officials from the Ministry of Housing and Local Government (MHCLG) visited our site on 23rd October 2018 to see first-hand the impact of their European Regional […]
Energy Works (Hull) Ltd can confirm, following extensive testing works, grid synchronisation has been signed off by Northern Powergrid on the 15th August 2018, to allow […]
Following installation works at the plant, the project has now received its Readiness to Receive RDF certificate from Fichtner Consulting Engineers, acting as the Project Manager. […]